AnsweredAssumed Answered

MS Project Upload To Clarity

Question asked by calth02 on Apr 28, 2011
Latest reply on May 16, 2012 by Slovak
I am trying to integrate a MS Project (2007) project plan into Clarity (8.1.5) and get the following error message: 'Duplicate task [59] found. Cannot continue save.' I'm not sure how this is possible if MSP autonumbers tasks. I also verified manually that there are no duplicate task IDs. Any thought?

TIA,

Tom

Attachments

Outcomes