Locking Finish Dates to Projects

Question asked by jschuff on Jun 10, 2011
Latest reply on Jun 14, 2011 by jj09
We have noticed that when a resource manager allocates their resource to a project or Other Work past the finish date of the project, Clarity pushes out the finish date of the entire investment.

My original assumption was that Clarity would not allow people to allocate resources past the finish date of the project, but the assumption has been proven wrong.

Does anyone know how we have a "locked" finish date on the project that cannot be shifted by an accidental typo from a resource manager when they are allocating resources on the project?

Any help would be greatly appreciated as I have a lot of clean-up work today to fix errors on projects.

Jenny