Question asked by Sankhadeep_DC on Jun 15, 2011
Latest reply on Jun 16, 2011 by Sankhadeep_DC
I think this was discussed previously, but I could not find the correct thread.
What is the impact of changing the resource calendar for a large number (`100) of resources?
1) Impact on timeslices: would availability slice be recalculated?
2) Impact on project plans? What would be the impact on project plan? If the new calendar which will be assigned to the resource has a different set of public holidays, would the project plans be affected?

Any other impact which I should keep in mind?