Actual Hours from WIP and Team Tab not matching - Help!

Question asked by DevK on Jul 8, 2011
Latest reply on Jul 8, 2011 by another_martink
Hi All,

We are noticing that the Actual Hours displayed on the team tab (For All Active/Inactive Resources) of a project and those available in Cost Plan do not match. This was observed after latest timesheet/financials were posted to the project.

The Actual Hours from the CP match the hours booked on Timesheets. However, the assignment actual hours do not match the timesheets. We saw the Actuals from Assignment are lesser than the CP actuals.

Can anyone please help us understand what might be the issue here? We are on v12, SQL Server, Windows OS.

Thanks
~Dev