AnsweredAssumed Answered

ETC & Actuals for Labor Resources

Question asked by seaneys on Jun 4, 2008
Latest reply on Feb 22, 2010 by Keri Taylor
Hello,

We're on 8.1 FP3.

Several of the out of the box portlets and expose a field called 'ETCs for Labor Resources'. The field looks extremely attractive, but ours appears to be using seconds (or at lease I suspect it is in seconds).

Has anyone seen a clean work around for this?

Steve