Actuals posted but Actual Cost at hierarchy page is zero.

Question asked by Canbulan on Jul 7, 2008
Latest reply on Feb 3, 2012 by another_martink
Hi Everyone, [left] I am working on  a Clarity 8.1 system with  fp3 installed.  We have the following issue: [left]   [left] After posting the timesheets, we can observe Actual values on workbreakdown page.  BUT  in the hierarchy page Actual Cost is 0. Also  on the  project properties page the Actual Hours value is still zero.   [left] Both project and resources are financially enabled. And we have already run the following jobs:
-post timesheet
-post transactions to financials [left] What can be the reason? Is there any other jobs to be run to see the Actual Costs? [left]   Note that we also tried the same on the Sandbox. And the result is the same.   Regards  Cem Canbulan  ccanbulan@meteksan.com.tr    
[left]   [left]