AnsweredAssumed Answered

How to stop an Resource entering time against an particular task

Question asked by sundar on Sep 17, 2008
Latest reply on May 25, 2016 by JRGieck2015
Hi, How to stop an Resource entering time against an particular task.The task is assigned to 2 resources and one resource res1 should notenter time against the task but the other resource res2 should.So we can't uncheck the open for timeentry in the Task.The resource res1 has put actuals against the task.He still has to enter time against an different task in the project so at the resource level we can't uncheck the open for timeentry for that project.How to achieve this,any ideas pls.... sundar