8.1.1 upgrade and use

Question asked by rkljr on Oct 28, 2008
Latest reply on Nov 28, 2008 by martink1
Is anyone using 8.1.1 in production?  We are interested in upgrading from 8.1.0 to 8.1.1 and have upgraded our development environment only at this time. We have identified at least one issue that prevents us from moving forward and are interested in others experiences.   The one issue we have is that it is not possible to repopulate from a resource plan for projects that use a currency other than the base currency.   What issues have you had during your upgrade?