AnsweredAssumed Answered

Is there a way to modify "Working/Non Working Days"?

Question asked by Phil_S on Jun 19, 2009
Latest reply on Jun 23, 2009 by Dave
I have been asked if there is any way of getting Clarity to accept an external update of which days in a resource's calendar are going to be either working or non-working. The aim would be to get an external leave-approval application to provide this data every so often and hence save our administrator from having to enter it manually for a number of users.  To me it looks as if the relevant data may be stored in table PRCALENDAR - but it looks as if the most likely source (column PRVALUE) is stored as a BLOB. To me eyes the chances of success look slim at this point but I would be interested to hear if I am wrong in my assumption about where the info is stored or if anybody has succeeded in getting something like this to work.  Can I be the only person who would very much like to be able to do this?  thanks

Outcomes