AnsweredAssumed Answered

Clarity - MSP Issue

Question asked by aashish on Jul 15, 2009
Latest reply on Jul 20, 2009 by Chris_Hackett
We use MSP as our scheduler for our Clarity R12 system. I have begun to notice that when changes are made in MSP and saved to Clarity, the following fields are changed when you re-open them in Clarity:

a. Duration
b. % allocation associated to the resources
c. Finish Dates

This behavior typically occurs on:

i. tasks that have actuals posted against them and
ii.tasks that have dependencies on the ones stated above

I set the Task Type of "Fixed Duration" first and then to "Fixed Units", but the problem still occurs. In both instances I unchecked the "Effort Driven" option.

Has anyone else experienced this behavior? How have you solved this?