Attached you will find screen prints.   We have a project where a resource applied 12 hours at a rate of 86.78.  A manual Transaction Entry was created and has been full posted to the system. However, in OWB the removal of this work effort/financials isn’t processing and it is still showing the original work effort and financials.   The problem is that it isn’t matching the project transaction inquiry report. The PM's utilize the OWB to track the financials for the project but creating custom views that total the information in OWB.   Please let me know if this is an issue with a setting in the system or if there a job that needs to run.   This isn't the only project.   Thank you    