ClarityUser

Getting Tasks constraints in MSP

Discussion created by ClarityUser on Jan 31, 2010
Latest reply on Feb 3, 2010 by Chris_Hackett
Hi,When I retrieving project to MSP 2007 in some cases i'm getting tasks which were defined as ASAP as Start no earlier then.CA's support explain on that is that Carity reschedule incompleted tasks, and define them with a constraint.  CA response: " Our MSP macro calls API code similar to MSP's Tools\Tracking\Update Project\ select Reschedule Uncompleted Work To Start after . This moves all unused work to after this date, and applies the constraints. We do this to insure no ETC (work) is prior to the Act Thru Date"   any experience with that? is there a way or work around to remove this phenomenan?    thanks,  Ron