Adding Resources or Roles to the Project Staff

Question asked by Keri Taylor on Mar 15, 2010
Latest reply on Mar 16, 2010 by sundar
Hello,I am needing some help. We are adding Roles to the Project staff as placeholders for named resources. Recently, we have now added multiple roles on a plan.. For example, a project’s “programmer (1)â€? and “programmer (2)â€?. When running a custom project forecast report in the past when only 1 role "programmer (1) is added the report calculates properly. Now, when adding multiple roles For example, a project’s “programmer (1)â€? and “programmer (2)â€? the report is now adding the ETC's multiple times. Lets say 1 and 2 have 1032 hours of ETC each. Here is OWB view for the programmer (1) & (2)   res id, ETC hours
programmer 1, 1032
programmer 2, 1032     while using a timescale spread, the hours would break down in OWB like this... Jul, Aug, Sep, Oct, Nov, Dec
176, 168, 176, 160, 176, 176   Now on the report...it looks like this: Jul, Aug, Sep, Oct, Nov, Dec
704, 672, 704, 640, 704, 704   so..its taking 176 + 176 X 2   = 704  And i have no clue as to why... everything totals properly when named resources are used & only lets say 1 role. It gets hosed when multiple roles are assigned to the project. Ie. programmer (1) and programmer (2)  any help would be greatly appreciated.    Keri