Im curious where the Budgeted cost comes from. Per the definition it comes from the budgets plans or swag, or planned cost. However, I a project with no swag, financial plan or baseline. Yet it has a budgeted cost.  We looked in the old system 7.5.3 and we see under the budget swag the budgeted cost field. HOwever, in the version 12.0.4 we only see planned cost. Are they the same or is budgeted cost a hidden field?    