AnsweredAssumed Answered

Risks / Issues "Roll up" to Master Projects

Question asked by ca.portal.admin on Apr 29, 2010
Latest reply on Apr 30, 2010 by Dave
I'm looking for an easy way to "roll up" risks and issues from sub-projects to a portlet on their master project.   I do not see any out-of-the-box portlet or query that would provide me that data.  i.e. If I have a master PROJECT A and a sub-project of it is PROJECT B, and I create Risks/Issues at PROJECT B level, then I can “roll upâ€? those Risks/Issues to see them in a portlet within the master PROJECT A?  I’m sure this will require a custom query.   Has anyone attempted this, and if so, would you be willing to share your NSQL code for "rolling-up" risks (or issues) from sub-projects?   I'd like to create a portlet based on this query that would allow the user to filter on Probability, Impact, and Calculated Risk score.    Any help would be greatly appreciated!