Actuals cost is ZERO for some assignments in task

Question asked by PrabhuRVP on Jul 10, 2014
Latest reply on Jul 11, 2014 by tanch10

Hello All ,

 

There are 4 resources assigned to a task with same financial properties. Project is also financial enabled. Rate matrix is also well defined .

 

The issue is Actuals cost is calculated only for 2 resources and for other two resources it is 0.

 

I am not able to understand how the actuals cost are calculated in Clarity.

 

Please anyone help me to understand this case

 

Many Thanks in Advance

 

Regards,

Prabhu