Hi guys,
I realise there are numerous threads on this but none seem to relate to what I'm seeing.
I am testing this integration tool on a Windows 7 machine.
SP1
64 bit O/S
Microsoft Project version 14.0.6023.1000 (32 bit)
JRE 7 is installed and configured in the PATH variable in Advanced Settings - Environment Variables.
When I open a project in Clarity, choose Open in Scheduler - MS Project opens but no project info is pulled from Clarity..
I have checked that the add-in is enabled.
I also see the following error:
SchedLink MFC Application has stopped working
A problem caused the program to stop working correctly. Please close the program.
I have a case open but thought I'd share here as well to see if anyone has experienced similar. Any help much appreciated - thanks!