AnsweredAssumed Answered

omitting start_times in WAAE

Question asked by jhill5.5 on Aug 22, 2014
Latest reply on Mar 20, 2016 by sandipkumarmahakud

If I omit the start_times field but set a calendar and set the date_conditions flag to true, will WAAE treat the job as having a start_times of 00:00?  We're seeing some unexpected behavior when the job has dependencies but no start_times, but we before we exhaustively run this down I wanted to be sure what the expected behavior was.

 

Thanks.

 

11.3 SP1, if that's relevant.

Outcomes