Hi,

 

There is 1 specific environment where all project (task) in OWB -> Gantt bars are shown in GREY no matter what the task status is.

According to OWB color settings, grey indicates "task lock for scheduling? -> yes".

 

I've used same OWB to open projects from other environments.. and I don't have that issue.

 

Not sure why OWB thinks tasks are locked. I made sure:

++ sercurity.logs is empty

++ tables empty: PRJ_tentative_projects and PRJ_tentative_tasks

++ Task is not Lock in Clarity UI before launching it..

 

Not sure what else needs to be checked. Any idea?