How to determine a Task Finish date changed manually vs MS Project upload

Question asked by fglarkin Employee on Aug 25, 2014
Latest reply on Aug 26, 2014 by fglarkin

Working with Clarity 13.3 on Oracle, On Demand

 

Customer wants to be notified when someone changes the Finish date on a Task. They use MS Project frequently to modify the schedule. I created a process that starts when Finish is changed, and found that it starts on all Tasks in a Project where the user saves changes from MS Project, even if only one Task actually had a change to the Finish date. Is there any way to distinguish which Task actually had a change to the Finish date in these circumstances?

 

Thanks.

 

Fred Larkin

Clarity Functional Consultant