lorenwatts

DUEOUT use relative time rather than absolute

Discussion created by lorenwatts on Sep 11, 2014

Is there a way to capture and use a relative time, such as the time a job finishes?

I need to use DUEOUT with a FILE_TRIGGER, and have the time reference one minute after the predecessor job finishes.

 

RELDELAY is not what I need.

 

Any time reference I find only is in relation to the Event, not an object in a member.

 

NOW PLUS 1 MINUTE   

This would be one minute after the scheduled time of the Event.

REALNOW PLUS 1 MINUTE   

This is one minute after the trigger time of the Event.

ESPAHH - hour

ESPAMN - minute

Variables starting with ESPS represent the scheduled trigger time and date for the event.

ESPA represent the actual trigger time and date for the event.