FTE Calculation in Resource Workloads portlet

Question asked by Akhil.Kakkar on Sep 19, 2014
Latest reply on Sep 19, 2014 by urmas

Hi there,

 

We have been onboarding few new teams and setting up their availabilities. We are unsure how the Resource Workloads portlet is calculating Availability Rate.


This is what we did:

1 - Created a new calendar - NEWCAL.

2 - Set the shifts in this new calendar so that its 7.5 hours/day. (8:00-12:00, 1:00-4:30)

3 - Updated a resource's base calendar to NEWCAL. Clarity updated the availability field on resource profile to 7.5 (It was 8 by default when the resource was created)

4- Went to the resource workloads portlet, and configured it. Configure -> Fields; In the Allocation field, selected Availability rate. Saved the change.

5 - In the Portlet Options, changed the work effort unit of measure to FTE.

 

When I go back to the portlet and filter for the resource, Clarity shows me 0.94 FTE. I would have expected 1. Why is it calculating FTE as 7.5/8. What do I need to change such that it shows 1 FTE.


Regards,

Akhil