Clarity

  • 1.  Resource Availability report shows no data

    Posted Oct 14, 2014 12:11 PM

    The Resource Availability report shows no data. It's a CSP report.

     

    Clarity version = 13.3.0.286 08 6

     

     

    NJ



  • 2.  Re: Resource Availability report shows no data

    Posted Oct 14, 2014 12:18 PM

    I checked the below -

     

    https://communities.ca.com/message/98330259#98330259

     

    The "WEEKLYRESOURCEAVAILCURVE" time slices are available.



  • 3.  Re: Resource Availability report shows no data

    Posted Oct 14, 2014 12:20 PM

    Rollover Interval          Monthly

    From Date                 1/1/2014

    Slice Period               Weekly

    Number of Periods      130

     

    NJ



  • 4.  Re: Resource Availability report shows no data
    Best Answer

    Broadcom Employee
    Posted Oct 14, 2014 12:42 PM

    Hi NJ,

     

    Please check the pre requisite below

     

    Report Prerequisites:

    • Resource availability amounts display if the resource has availability defined and meets the parameter criteria. The availability amounts are determined by the resource calendar.

    • The availability amounts are calculated based on the time slices with the name MONTHLYRESOURCEAVAILCURVE and WEEKLYRESOURCEAVAILCURVE (Administration/Data Administration-Time Slices). These time slices must be configured to cover the periods displayed in this report or the report will not display data for those periods.

    • The report has a parameter that allows you to run the report by weekly periods. For period type of week to display data, there are two places in Clarity that must have consistent start days of the week: (1) The start day of the week for the report column headings is retrieved from the First Day of Work Week field set in Clarity (Administration/Project Management-Settings) and (2) The time slices referenced by the report must all start on the day that you set as the first day of the work week. For example, if you set the first day of the work week field to Sunday (Administration/Project Management-Settings), then the weekly time slices referenced by this report must also be set to start on Sunday.

     

    The time periods that display in the report and the availability amounts being converted to FTE depend on the report calendar table. This table is populated by running the Update Business Objects Report Tables job with the update reporting calendar option checked. This job populates calendar periods and calculates FTE amounts based on the availability of the resource with Resource ID of 'admin' and the time slice with the name MONTHLYRESOURCEAVAILCURVE (Administration/Data Administration-Time Slices). This time slice must be configured to cover the periods displayed in this report or the report will not calculate FTE data for those periods.

     

    Hope this helps

     

    Regards

    Suman



  • 5.  Re: Resource Availability report shows no data

    Posted Oct 14, 2014 03:52 PM

    Thanks Suman , will check and get back

     

    NJ



  • 6.  Re: Resource Availability report shows no data

    Posted Sep 23, 2016 08:56 AM

     How to set job priority?



  • 7.  Re: Resource Availability report shows no data

    Posted Sep 23, 2016 09:32 AM