Has anyone else experienced this?

 

Requisition: Allocation on goes to zero after the named resource is selected and booked.  In the end, the resource does not get added to the team tab.

 

Here are the steps to recreate:

1.  Add a role to the team tab

2.  Go to the properties for the role

3.  Add a planned Allocation date range and % allocation

4.  Create a requisition (requisition type = Request Resources)

5.  Click on Create and Open button

6.  Email goes to booking manager

7.  Go into requisition, click Resources tab

8.  Click Add button

9.  Select named resource

10.  Click book button

 

Expected results:  The role allocations go to zero, the requisition shows the booked resource with populated allocation, date range, the Named resource is on the Team-staff tab with proper allocation

Actual results:  The role allocations go to zero, the requisition shows the booked resource with zero allocation, the Named resource does NOT appear on the Team-staff tab