Show financial values in project properties

Question asked by Nei_Lojas_Renner_SA on Jan 14, 2015
Latest reply on Jan 14, 2015 by Nei_Lojas_Renner_SA

Hi Communitie!

 

We need following information  at project´s propertie page:

 

Actual Cost.........................................: ok = I have created a calculated attrib Sum(aggr_actual_cost) to show total realized. 

Cost total............................................: ok = Already exist in Clarity  [Planned Capital Cost] to show total planned cost.

Actual Cost - Current Year.....................: ? = We need to know how much project spents in current year.

 

So, how can I put this ACTUAL COST  - CURRENT YEAR in project´s propertie page?

Looks like a query solution, but in this case I am afraid for database performance issues.

 

Best regards,

 

Nei Villas Boas