Actuals for expense resources entered via microsoft project are doubled in CA PPM

Discussion created by Mark101 on Jan 28, 2015
Latest reply on Feb 3, 2015 by Mark101

Hello,

we are using CA PPM (13.3) with MS Project 2010 as scheduling application. We're not using timesheets and all actuals are entered directly into CA PPM via MS Project. We're also entering actuals for expense resources this way. Now we noticed that actuals entered in MS Project for expense resources are doubled in CA PPM. This is not the case for labor resources, just expense resources.

 

So when we enter actual work of 1000 in MS Project, the acuals field in CA PPM shows 2000.

 

any one has an idea why happens?

 

thanks,

Mark