Actual hours entered via OWB or MS-P not shown in cost plans

Question asked by Mark101 on Feb 12, 2015
Latest reply on Feb 13, 2015 by Mark101

Hello,

 

we enter actual hours spend on task direclty into MS Project/OWB. we're not using timesheets. And we didn't want to use the transaction to enter hours on tasks. The actual hours get processed correctly every where we look in Clarity, including the hours * hourly rate. The ACWP, Actuals etc get filled as expected. The problem we're facing is that these actuals are not being displayed in the cost plan or the budget plan.

 

The Import Financial Actuals job is running; the Post Transactions to Financials is also running and the timeslicing job.

 

Any idea why these actuals are not showing up in the cost plans?

 

thanks,

Mark