Key Milestones in Portfolio Management

Discussion created by robert.muir on Mar 17, 2015
Latest reply on Mar 18, 2015 by am1

We are exploring use of Portfolio Management and need to show the Key Milestones of our projects.  Ideally we would use just two of the 6 Key Milestones we use for Start and Finish Dates instead of the standard Start and Finish.  This is because two of our milestones are used for our TTM measure.  The launch milestone can finish months before overall finish date of the project.

 

Has anyone managed to get this into the Portfolio views, standard or within the PMO accelerator portlets?