Should making changes on a resource's calendar change the capacity shown on "Capacity vs. Demand by Resource" report

Question asked by navzjoshi00 Champion on Mar 24, 2015
Latest reply on Mar 27, 2015 by navzjoshi00

There is a resource for which the RM has marked the next 3 months as "No Work Day". However, when the "Capacity vs. Demand by Resource" is run, the capacity still shows as 1. Is this as designed or should making changes on the resource's calendar change the capacity shown on "Capacity vs. Demand by Resource" report ?

 

NJ

Outcomes