Updating Project Assignment ETC via XOG

Question asked by whole_milk on Apr 12, 2015
Latest reply on Apr 19, 2015 by whole_milk

Team:

 

I am able to update the ETC of a project's task assignment via XOG for a resource. However, when I go to the timesheets of the same resource where the task is used. I see that the ETC value I xogged in is not showing up there in the ETC column.

 

However, if I manually enter the ETC on the project's task assignment from the front end, it works as expected on the timesheet.

 

Any ideas?