Time Scale Value Virtual Attribute on Assignment Object Portlet?

Question asked by Robert Ensinger on Apr 16, 2015
Latest reply on Apr 20, 2015 by Robert Ensinger

Hi all.

  I need to make a grid portlet with a time scaled view of non-labor costs on projects as entered with non-labor resources on the WBS. What's the right tool for this job? I've found that making a grid porlet from the Assignment Object Data Provider gives me the data I need - only it doesn't look like I can create the Time Scale Value virtual attribute.

 

  Any quick ideas? Do Tasks and Assignment object data providers not support the TSV feature?

 

Project Object:

time_scale_value_project.jpg

 

Tasks and Assignments:

time_scale_value_task.jpg