Question asked by GermanK on Apr 27, 2015
Latest reply on May 7, 2015 by Michael Thibault

Hello Everybody:

 

Here is the deal.

 

Clarity 14.2

Oracle Linux Server Release 6.6

DB Oracle 11G

This is an upgraded database from 14.1 to 14.2

 

% Complete adds zeros:

 

Steps to reproduce:

  1. Create a new Project.
  2. Add tasks
  3. Change % Completed from 0 to any value for example 25

 

 

1.jpg

3. Click Save and the value changes to 2,500%

 

2.jpg

NOTE: Percentage Complete Calculation is set to Manual

 

3.jpg

What is going on ? Thanks in advance for your ideas and inputs