    Does anyone have any processes somehow created that triggers based on additions or updates to the team tab of a project. The team tab is not an object you can associate to a process ootb ,so I'm just curious if anyone has designed anything other than a scheduled job. I'm looking for something more automatic.



  • 2.  Re: Team Tab Process

    Posted May 29, 2015 11:01 AM

    Hello Serge,

     

    As far as I know, you do not have TEAM object as an option to associate process with. But you can create process with Project as primary object and you have an option to choose team object attributes in the start condition builder.

     

    Regards

    Chandrani



  • 3.  Re: Team Tab Process

    Posted Nov 05, 2015 11:15 AM

    that's correct, you have the option to select team object attributes but they do NOT actually work as far as I know.

     

    For example, I did the following test

    Object: Project

    Start Conditon: Team (subobject) - update: Capitalzation % > 0

    start step: set charge code = capital

    Finish

     

    I am updating the cap % on the team record and no process kicking off and charge code is not updated