CA PPM Tuesday Tip: Identify resource management permissions.

  • 1.  CA PPM Tuesday Tip: Identify resource management permissions.

    Broadcom Employee
    Posted Jun 09, 2015 09:14 AM

    Many companies do requisitions in different ways.

     

    At some companies the people that perform hard-booking of resources are the Resource Managers rather than the Project Managers.

     

    If we look for the permission in order to do hard-booking we have the following access rights.

     

    Resource Management        Resource - View - All

    Resource - Hard Book All

    Resource - Soft Book All

    Resource - Update Skills - All

    Project - Create/Edit Requisitions - All

    Project - Attach Requisitions Entry Resources - All

    Project - View Requisitions - All

     

    This info is obtained from the Access Rights Reference Guide, from <https://support.ca.com/cadocs/0/CA%20Clarity%20PPM%2014%202%2000%20%20On%20Premise%20-ENU/Bookshelf_Files/HTML/access/2179061.html>

     

    Now when you add these permissions and try to book a resource, it will show the following error.

     

    Tuesday TIP.png

     

    As the error indicates show there are missing access rights and this access is:

     

    Project - View Management - All

     

    This permission allows user to view the general and management properties and processes on all Projects which have been enabled for management.

     

    So in addition to the Hard Book rights the resource manager also needs to have access to see project Management information in order to book a resource.