AnsweredAssumed Answered

Has anyone noticed that Baseline Usage is not displaying correctly (in v13.3 or v14.x) on the Team Tab if you have multiple generic roles allocated onto project?

Question asked by nosreme on Jun 18, 2015
Latest reply on Jun 25, 2015 by eugene.mcphearson

We have a tasks with multiple "Engineer" roles.  Engineer, Engineer (2), Engineer (3) and when you baseline the project or tasks, their ETC's are correctly moved to Baseline Usage in OWB.  When you save this information back to Clarity, the baseline usage is only displaying for one role in Clarity's Team tab.  We use Clarity generic roles extensively as we tend to source projects from multiple engineering locations around the world. We transfer this work from the role to the resource as those actual resourcing decisions are made.   Let me know if anyone else has noticed this?