We use the GD Transaction Adapter to import our actuals from our timekeeping system of record Oracle for our company. We are looking into how we can use the Cost/Rate matrix for project cost plans and during testing it appears that the Cost/Rate matrix is not being used to get the rate for a role or resource. If i use the Clarity Timesheet for entering hours the Cost/Rate matrix is being used. Since our import of actuals from Oracle via the GD Transaction Adapter uses/sends/maps a rate with each tranaction does that override the cost/rate matrix defined on the project setting page under Labor Transaction Matrix? and therefore I cannot use the Cost/Rate martix defined. Thank you!!!