  • 1.  Role/Resource availablity

    Posted Aug 13, 2015 10:17 AM

    Hi,

     

    For Roles, we can see the Resource availability in Resource allocation page, like I filter by Role (selected one role) and I click on Allocation -> Details page, there Resource availability is empty.

    Is clarity designed like we can only able to see Resource availability and not Role based availability?

    Please clarify this.



  • 2.  Re: Role/Resource availablity

    Posted Aug 13, 2015 11:15 AM

    Check this -

     

    CA PPM Tuesday Tip: Resources with or without Availability

    https://communities.ca.com/message/241792825#241792825

     

     

    Expense Resources and Roles will always have zero availability. 

    It is not possible to configure an Expense resource or role with availability. 

    You do not use Expenses for tracking work effort or hours.

    However, Equipment and Material and Labor Resources all can have zero or non-zero availability. 

    These types of resources can be scheduled within the investment for performing work or in the case of Equipment or Materials, can be scheduled for hours of usage.

     