AnsweredAssumed Answered

PENDING ESTIMATES: In OWB we have have 5 resources with different ETC and 1 out of 5 resource has requested more ETC for task via timesheet. This extra requested ETC comes as pending estimtes in OWB. While accepting pending ETC on the task, the ETC for ot

Question asked by Ashwin.Soni1 on Aug 20, 2015
Latest reply on Aug 20, 2015 by urmas

In OWB we have have 5 resources with different ETC and 1 out of 5 resource has requested more ETC for task via timesheet. This extra requested ETC comes as pending estimtes in OWB. While accepting pending ETC on the task, the ETC for other 4 resources become ZERO. Can anybody advise the issue. Thanks in advance

Outcomes