AnsweredAssumed Answered

Using 'sched 8th-last day of month' at event level

Question asked by Loraine on Aug 21, 2015
Latest reply on Sep 3, 2015 by sicma03

Am I using the correct syntax at the Event Level or am I seeing things?

When I type 'SCHEDULE AT 11.00 ON 8TH-LAST DAY OF EACH MONTH  STARTING AUG 24 2015'  the event rewrites the SCHED statement as:

"SCHEDULE AT 11.00 ON 8TH-LAST DAY OF EACH MONTH -

         STARTING SAT 22ND AUG 2015"     

 

The NEXT 10 displays of the event name confirm that the event will first trigger on Sat Aug 22 even though I specified a STARTING date of Monday Aug 24.

 

To get around this I've added NOSCHED 11.00 ONCE statements for Sat and Sun.

 

Any suggestions on the correct syntax to use?

Thanks! Loraine

Running CA Workload Automation ESP Edition r11.4.

Outcomes