Hi
We have one fixed task in OWB without any resource and actuals, the issue here is the start date of the task changes automatically. We have not doing any autoscheduling. Can anyone tells the possible causes. Tanks.
Hi Ashwin.soni,
Can you please let me know which version of CA PPM are you using right now? Also, let me know the version of OWB where you are facing the problem.
Thanks,
Abhisek Dhar
Hi Abhishek,
We are using Clarity 13.3 & OWB 2.1.1