AnsweredAssumed Answered

default cost type of "cost plan".

Question asked by chison.cai on Sep 9, 2015
Latest reply on Sep 10, 2015 by chison.cai

Hi,

 

In Clarity r13.3, if "cost type" is not one of the "grouping attributes", Clarity will calculate the total cost of the "cost plan" as "Planned operating cost", and displays in "Financial Summary" screen.

 

Is it able to change the default cost type to "capital cost" ?

 

I tried to modify the "cost type" in settings of project but doesn't work.

 

Thanks.