Dicrepancy with the Baseline cost

Question asked by navzjoshi00 Champion on Sep 11, 2015
Latest reply on Sep 11, 2015 by Kathryn_Ellis

In some cases it is less the actual cost of the project. To my understanding the baseline cost is equal to Actual + Remaining Assignment cost.

 

Digging into this issue further I found that Rate Matrix setup is setup with different Values in Rate, Standard Cost and Actual Cost.

 

Does the different rates affect the baseline?

 

I have checked the WIP and totalcost and actualcost values in WIP are different. Also not sure where else would either of the rates impact (Cost Plans, Cost on Projects, Tasks, ...etc??)

 

Any help is highly appreciated.

 