AnsweredAssumed Answered

ETC of 0.000016 - Rounding Error

Question asked by timconstan on Oct 19, 2015
Latest reply on Jan 25, 2016 by Dale_Stockman

When I auto scheduled my project this one task's end date was moved out past today even though the task was showing 100% Complete, a status of Completed, and an ETC of 0.00.


When I clicked on the ETC for the task I saw that it was 0.000016.  When I typed over the ETC and changed it to “0” and auto scheduled it worked right.


Is there a way to get Clarity to round the ETC down to 0 when it's so close to 0?

 

Thanks.

Outcomes