  • 1.  Stop task finish date from moving?

    Posted Oct 22, 2015 12:10 PM

    Is there any possible way to force task finish dates to not move when no etcs are left?

     

    • We have a project that has a finish date of 12/31/2016.
    • Tasks were created with the finish date of 12/31/2016.
    • ETCs are not being used for this project.

     

    After time posts, the task finish date is brought back to the most current week. Is there any way to keep this from happening? We tried setting the fixed flag but the same behavior happens after time posting.

     

    Thanks!



  • 2.  Re: Stop task finish date from moving?

    Posted Oct 22, 2015 04:31 PM

    Experiment (carefully) with fixed loading pattern instead of fixed duration (flag).