Enhancement Request: Task actual finish date that is different than the date the last hour is posted on assignments

Discussion created by CalSTRS on Oct 29, 2015
Latest reply on Oct 30, 2015 by urmas

Project Managers have requested that they have the ability to set the actual finish date on a task (in Clarity and MS Project) that is later than the date the last hour is posted on assignments. The Project Manager should be the one to determine when a task is completed, and just because the last hour is posted on an assignment does not mean that work was completed satisfactorily. The current work around is to use a milestone to mark the actual finish date, but you lose the duration variance of the task.