What is the best way to get a total internal vs. external costs on a project?   (Similar to the way the Financial Summary page gives total Capital vs. total Operating Cost.

  • 1.  What is the best way to get a total internal vs. external costs on a project?   (Similar to the way the Financial Summary page gives total Capital vs. total Operating Cost.

    Posted Nov 06, 2015 05:18 PM

    What is the best way to get total internal vs. external costs on a project?   (Similar to the way the Financial Summary page gives total Capital vs. total Operating Cost.)



  • 2.  Re: What is the best way to get a total internal vs. external costs on a project?   (Similar to the way the Financial Summary page gives total Capital vs. total Operating Cost.

    Posted Nov 16, 2015 02:03 AM

    When you say "internal vs. external costs", do you mean "employee vs contractor" ?

     

    NJ



  • 3.  Re: What is the best way to get a total internal vs. external costs on a project?   (Similar to the way the Financial Summary page gives total Capital vs. total Operating Cost.

    Posted Nov 16, 2015 11:04 AM

    I would like to summarize all external costs, which includes external labor / contractors, but also all dollars paid outside the company such as travel, training, professional services, hardware, software, equipment, and materials.

     

    Mark W. Casey

    IT-PMO Manager

    Schenker Logistics, a Division of Schenker, Inc.

    469 644-5834

    Mark.Casey@dbschenker.com

     

    Sent from my iPhone



  • 4.  Re: What is the best way to get a total internal vs. external costs on a project?   (Similar to the way the Financial Summary page gives total Capital vs. total Operating Cost.
    Best Answer

    Posted Nov 17, 2015 03:41 PM

    Mark,

     

    This would depend on the financial set up of the resources (inc non labour)

    If you have set these resources (travel, training etc) with appropriate transaction classes, then in your reporting you can group these classes into "internal" and "external" based on your business rules.

    I.e. transactions for internal labour would be associated with intlabor and external with extlabor

    if intlabour then 'internal' etc

    #helpinghands



  • 5.  Re: What is the best way to get a total internal vs. external costs on a project?   (Similar to the way the Financial Summary page gives total Capital vs. total Operating Cost.

    Posted Nov 17, 2015 03:52 PM

    Thanks, we are using that approach via Resource Classes and writing a query to summarize the totals.



  • 6.  Re: What is the best way to get a total internal vs. external costs on a project?   (Similar to the way the Financial Summary page gives total Capital vs. total Operating Cost.

    Posted Nov 17, 2015 04:23 PM

    that's great to hear