Hi All,

 

We are using Clarity 12.0. When updates to project are xogged by our application, the proxy task in the master project is not updated.

For example, when finish date of the project is updated by XOG, the corresponding proxy tasks's finish date in the master project is not updated.

But when updating the project finish date from Clarity UI, the proxy task's finish date is updated as expected.

 

So the question is why the Project XOG is not updating the project's proxy task but  project updates through Clarity UI is updating the proxy task?

Is there any addition tag required when xogging?

 