Open for Time Enrty Flag getting unchecked in Staff Properties Page

Question asked by Aradhana.santra on Dec 2, 2015
Latest reply on Dec 2, 2015 by Kathryn_Ellis

Hi All,

 

We are using Clarity 7.5.3. There is resource who is allocated to a specific project with 100% allocation. Booking Status is Hard and also ETC is there. The resource is Open for time entry as well as the Project is. Open for Time Entry flag is unchecked in Staff Properties Page so the resource is unable to book time for that Project. We have checked the flag but its got unchecked again overnight. Any idea why this is happening?

 

Also, could you pleas

 

Thanks,

Aradhana