Costplan Planned Cost vs. EAC T in Taks List

Question asked by SimonJacobsen on Dec 22, 2015
Latest reply on Dec 28, 2015 by navzjoshi00

Task list for tasks with no subtasks shows:

The EAC (T) shows 1.897.273,43

 

My Cost Plan shows:


Planned Cost 1.720.142,26

 

I would expect those two amounts to be equal. However, I have been told that if rates of the resource class change during the project the two amounts might differ as they do here. I just don't understand why.