We are seeing a negative amount in the ACWP field on a specific resource when looking at the details of a task.
There are no posted actual values. This is a terminated resource - and in looking at past time sheets - he did originally post time to the task, then it was adjusted off in a subsequent time sheet.
This negative amount is impacting the correct calculation of the task.
Any ideas on how to remove the negative amount?